Back to calculator ↑What this tool estimates
The tool works out the volume of joints in a wall where mortar fills the full depth of each joint. It suits clay bricks and solid blocks laid in conventional mortar. It isn't for thin-bed AAC mortar or adhesive, where you should use the maker's coverage per bag. It isn't for hollow blocks bedded only on their outer edges either: for those, the result is an upper estimate. Calculate render (ฉาบ) separately.
How the estimate works
The joint fraction is 1 − (block face area ÷ module area). Multiply that by the net wall area and the wall depth to get wet mortar volume. Then add the allowance and divide by the bag's mixed yield in litres.
Using the defaults (5 × 2.4 m wall, no openings, 0.6 × 0.2 m face, 0.1 m depth, 10 mm joints, 15 L per bag, 15% allowance): the module is 0.1281 m² and the face is 0.12 m², so the joints take up 6.32% of the wall face. That gives 12 × 0.1 × 0.0632 = 75.9 L, or 87.3 L with 15%, so 6 bags. With one door counted (10.2 m² net), it's 74.2 L and 5 bags. With 2 m² of total openings, it's 72.7 L and 5 bags.
| Unit (10 m² net wall, 10 mm joints) | Wall depth | Joint fraction | Mortar +15% | Bags at 15 L |
|---|---|---|---|---|
| 600 × 200 mm block | 0.10 m | 6.32% | 72.7 L | 5 |
| Concrete block 390 × 190 mm | 0.07 m | 7.38% | 59.4 L | 4 (upper estimate if bedded on edges only) |
| Clay brick 160 × 35 mm face (illustrative) | 0.07 m | 26.8% | 215.7 L | 15 |
Small bricks have far more joints per square metre, so a brick wall needs roughly three times the mortar of a block wall.
Bag yield or bag coverage
The 15 L default is an example of mixed volume. It isn't the bag's weight. Thai mortar bags usually state coverage instead, as m² of wall per bag for a particular block and joint. When your bag gives coverage, you don't need the tool's volume at all:
bags = net wall area × (1 + allowance) ÷ m² per bag.
For example, SCG Tiger AAC laying mortar (50 kg) is listed by a retailer as covering about 25–30 m² of 7 cm AAC block at a 3 mm joint. For a 10 m² wall that's under half a bag, which is far less than the 5 bags in the conventional-joint table. That gap is why thin-bed AAC needs its own product figure. Check the coverage printed on your bag.
Check the order
Match the mortar type to the block and to whether the wall is inside or outside. Don't mix more than the crew can use within the working time printed on the bag. Mortar that has started to stiffen has to be thrown away, which raises real consumption. Store bags dry and off the floor.
Limits
The formula assumes even joints through the full depth of the wall. It doesn't model corners, filling the hollow cores of blocks, ties or lintels. The 15% allowance is an editable margin, not a guaranteed yield. Laying a short trial section is the most reliable check.
Common questions
How many bags of mortar for a 12 m² block wall?
With the defaults (600 × 200 mm units, 10 mm joints, 0.1 m depth), about 87 L with allowance, or 6 bags at 15 L each. With openings deducted, it's fewer.
My bag says "ก่อได้ 25 ตร.ม." What do I do?
Use that coverage directly. For 10 m² plus 15%, that's 11.5 ÷ 25 = 0.46, so 1 bag. The coverage only applies to the block and joint it was measured for.
Can I use this for AAC adhesive?
Not reliably. Thin-bed AAC mortar uses joints of a few millimetres, so use the maker's coverage per bag.
Is the bag yield its weight?
No. Enter the wet mixed volume in litres. A 50 kg bag makes far fewer than 50 litres.
Why does brick need so much more mortar?
Small bricks mean many more joints in each m². In the table, joints take up about 27% of the wall face for bricks, against about 6–7% for large blocks.
Is render included?
No. Render coverage is usually printed as m² per bag at a given thickness. Calculate it separately.
Why 15% allowance?
It covers droppings, uneven joints and filling gaps. It's a starting figure. Adjust it after a trial section.